2015 Work Weekend
The 2015 Theta Chi work weekend at the fraternity house occurred Thursday through
Sunday, August 13th-16th. Sixteen alumni contributed their time and energies as well as
over twenty actives. These dedicated individuals concentrated on a predetermined list
of tasks that largely entailed painting, electrical, plumbing, carpentry and general
cleaning and repairs. Funding for supplies during these activities was provided through
the personal gifts of several Alums. In total, approximately $1,800 was spent with nearly
$1,100 left over to replace a badly needed window.
The physical effort contributed during this event was significant. Particularly since the
Actives were also in the process of preparing their living quarters for the upcoming
school year. The cooperation and camaraderie that prevailed during these four days
was indicative of a real team effort and one that was of great benefit to the Theta Chi
Hopefully, a further effort can be made next year to complete some of the remaining
tasks already identified in our Corrective Maintenance Plan. We would encourage
more alumni participation and if that is not possible, your financial support would be of
great assistance in helping us meet the challenge.
Following is the list of tasks that guided our efforts. We certainly accomplished more
than what we thought possible in four days. Over two-thirds of these projects were
completed. All because of Actives and Alums who cared to make a difference.
Hopefully, you can be a part of next year’s fun.
Steve Wylie, Class of 65’
 Replace knobs on metal cabinets - Completed
 Replace hardware on kitchen sinks - Completed (except for small porcelain sink)
 Clean all floor, sink and appliance drains - Completed
 Paint over leak stain in ceiling & gas lines - Completed
 General housekeeping -Completed
 Scrape & paint jamb areas around exterior door - Completed
 Touch-up paint on walls - Need to determine correct color before painting
 Refinish interior door - Completed
 Replace fluorescent light covers - Completed
 Replace fluorescent light bulbs - Completed
 Refinish shelves - Completed
 Paint sprinkler pipes - Completed
 Replace ceiling lights - Completed
 Replace floor molding - Not addressed at this time
 General housekeeping - Completed
 Paint Door jambs - Not addressed at this time
 Paint walls, ceiling and molding above stairway - Not addressed at this time
 Paint stair railing in foyer - Completed
 Organize internet equipment - Completed
 Repair wooden fire doors - Determined to be unnecessary
 Repair drywall - Completed
 Study/storage areas (clean-up/demolish) - Not addressed at this time
 General housekeeping - Partially completed
 Install chair rail - Completed
 Touch-up paint on walls & door jambs - Completed
 Touch-up paint on walls & door jambs - Completed
 Replace chairs - Completed
 General housekeeping - Completed
 Replace sink hardware - Completed
 Replace urinal - Determined to be unnecessary
 Replace light fixture above sink - Completed
 Replace floor tiles at entrance - Completed, (painted over gap instead)
 Repair efflorescence areas on wall - Completed
 Clean floor tiles - Not addressed at this time
 Replace floor molding - Completed
 Replace ceiling tiles - Not addressed at this time
 Install/refinish door trim - Not addressed at this time
 General housekeeping - Partially Completed
 Replace sink hardware - Completed
 Paint sprinkler pipe - Partially completed
 Seal & paint walls - Not addressed at this time
 Repair ceiling - Not addressed at this time
 Install lighting - Not addressed at this time
 Install shelving/cabinets - Not addressed at this time
 Tape & plaster ceiling - Completed
 Paint ceiling - Completed
 Replace lights/globe - Completed
 Replace vent cover - Completed
 Install door jamb & molding - Not addressed at this time
 Install door - Not addressed at this time
 Install floor molding - Not completed
 General housekeeping - Completed
 Place concrete barrier at top of stairs - Not addressed at this time
 Paint eastside doors - Completed
 Repair southeast door - Partially completed
 Insure proper roof drainage - Had been addressed earlier
 Repair trash barrier - Completed
 Paint patio furniture - Completed
 Mulch/weed flower beds - Completed
 Clean entryway closets - Completed
 Clean small basement storage area - Completed